1400 W. Monroe
1400 W. Monroe, Chicago
Architect: Booth Hansen, Architect
Contractor: Summit Design + Build, LLC
New Masonry
- Furnish, set-up, maintain, dismantle and remove all equipment (hydro-mobile scaffolding, forklift, tube scaffolding, ladders, hand tools, etc.) necessary for the new masonry portion of the project.
- Furnish and install modular sized face brick necessary for erecting new exterior masonry veneer as per options mentioned below. Brick to be installed in running bond using colored type ‘N’ mortar. Mortar joints to be tooled concave, brushed and tooled to a final finish. Soldier brick accents to be installed as per drawings.
- Furnish and install fully grouted bond beam courses as per structurals.
- Vertical reinforcement to installed as per structurals.
- Horizontal reinforcement to be M.G. ladder/hook type wire installed in masonry coursing every 16” O.C. vertically as per drawings.
- Furnish and install one (1) two-piece adjustable anchor every 16” O.C. for brick veneer.
- Install loose steel lintels furnished by others on project site as necessary.
- Furnish and install 40mil self-adhesive flashing over a 1½” stainless steel drip edge at the base of masonry walls and over openings in masonry with “weeps” installed in masonry head joints every 24” O.C. Furnish and install mortar trap at flashing locations as per drawings.
MISCELLANEOUS
- Price of masonry is based on Endicott Manganese Ironspot Smooth Modulars as per elevations (see alternate for cheaper option).
- Block walls are to be scraped clean upon completion of project.
- Chemical washing of new brick/stone masonry upon completion of project as necessary. Price of masonry does not include any masonry sealing.
- Price of masonry is based on being able to use hydro-mobile scaffolding to perform our work.
- All debris relating to our work to be cleaned and placed in refuse containers provided by general contractor on project site.