Northwood Station
372 Wood Dale Road, Wood Dale, Illinois 60191
Contractor: Holladay Construction Group LLC
Architect: PURE Architecture Studio, LLC
New Masonry
- Furnish, set-up, maintain, dismantle and remove all equipment (forklift, scaffolding, ladders, hand tools, etc.) necessary for the masonry portion of the project.
- Furnish and install 8” CMU necessary for erecting two (2) full height elevator shafts, two (2) full height stairwells as per drawings. Block is to be installed in standard running bond using natural gray type ‘S’ mortar. Mortar joints are to be tooled concave, brushed and tooled to a final finish.
- Furnish and install fully grouted bond beam coursing as per structural drawings.
- Vertical reinforcement to be as per structural drawings.
- Horizontal reinforcement to be mill galvanized ladder type wire installed in masonry coursing every 16” O.C. vertically.
- Furnish and install preformed gaskets within CMU for control joints per plans (caulking by others).
- Install elevator hoist beam and elevator inserts furnished by others on project site.
- Install hollow metal door frames furnished by others on project site.
- Furnish and install face brick and cast stone veneer surrounds, trims, at exterior of building as per drawings. Mortar joints are to be tooled concave, brushed and tooled to a final finish. Expansion/Control joints provided per plans at brick locations.
- Veneer to be anchored to substrate using one (1) two-piece adjustable anchor every 16” O.C. horizontally and vertically.
- Install steel lintels furnish by others on project site.
- Furnish and install Mortar Net (or equal) in wall cavity at the base of masonry walls and over openings in masonry as per drawings.
- Furnish and install 40mil self-adhesive flashing over a 1½” stainless steel drip edge at the base of masonry walls, over openings in masonry with plastic cell vent “weeps” installed in masonry head joints every 24” O.C.
- Waterproofing/Caulking by others
- Steel bracing/fire caulking/fire safing at top of walls to be furnished and installed by others.
- All debris relating to our work to be cleaned and placed in refuse containers provided by general contractor on project site.
- Chemical washing of new brick/stone masonry upon completion of project.
- Block walls are to be scraped clean upon completion of project.