Freddy’s Frozen Custard
Downers Westmont, Illinois
Contractor: BCCM Construction Group
Architect: Dan Winter
New Masonry
BUILDING VENEER
- Furnish, set-up, maintain, dismantle and remove all equipment (forklift, tube scaffolding, ladders, hand tools, etc.) necessary for the masonry portion of the project.
- Furnish and install a combination of Wellshire and Misty modular size face brick as manufactured by Summit Brick necessary to erect new masonry veneer walls on building and three (3) columns as per drawings. Brick is to be installed in standard running bond with soldier and rowlock accents using natural gray type ‘S’ mortar. Mortar joints are to be tooled concave, brushed and tooled to a final finish.
- Veneer to be anchored to substrate using one (1) two-piece adjustable anchor every 24” O.C. horizontally and 16” O.C. vertically.
- Install steel lintels furnish by others on project site.
- Furnish and install Mortar Net in wall cavity at the base of masonry walls and over openings in masonry as per drawings.
- Furnish and install matching thin brick at South elevation parapet returns.
- Furnish and install 40mil self-adhesive flashing over a 1½” stainless steel drip edge at the base of masonry walls, over openings in masonry and below rowlock sills with plastic cell vent “weeps” installed in masonry head joints every 16” O.C. Cell vent weep color to be gray to match mortar.
TRASH ENCLOSURE
- Furnish and install Wellshire modular size face brick as manufactured by Summit Brick with standard gray 8” CMU back-up necessary for erecting new trash enclosure walls as per drawings. Block and brick are to be installed in standard running bond using natural gray type ‘S’ mortar. Mortar joints are to be tooled concave, brushed and tooled to a final finish.
- Furnish and install fully grouted bond beam at the top of masonry walls with two (2) grade 60 #5 rebar installed.
- Vertical reinforcement to be one (1) grade 60 #5 rebar installed every 24” O.C. horizontally. CMU cores containing vertical reinforcing bars to be grouted solid.
- Horizontal reinforcement to be hot-dipped galvanized ladder type wire with integral veneer hook anchors installed in masonry coursing every 16” O.C. vertically. Veneer anchors to be installed every 16” O.C. horizontally.
- Furnish and install one (1) ½” x 8” galvanized anchor bolt in to top of masonry walls every 48” O.C.
- Furnish and install 40mil self-adhesive flashing over a 1½” stainless steel drip edge at the base of masonry walls with plastic cell vent “weeps” installed in masonry head joints every 16” O.C. Cell vent weep color to be gray to match mortar.